Gulf Star Marina is now open for business:

Gulf Star Marina is now open for business! After tons of hard work and dedication, the marina is now able to receive, store, and send out boats.

  • 1 June 2018

    Old Building Demolished

    After removing most of the metal and bolts from the old metal building, we pulled down the frame with a forklift. Then, we began cutting and hauling away the steel for recycling.

  • 30 August 2018

    Auger Cast Piles Installed

    We installed auger cast piles to help support the building on the area's soft and sandy soil.

  • 15 October 2018

    Continue Footer Form & Begin Footer Pour

    We began pouring our main strip footings.

  • 23 October 2018

    Continue Footer Form & Pour

  • 6 November 2018

    Crane Pit Excavation

  • 10 November 2018

    Crane Path Slab Forming

  • 13 November 2018

    Main Crane Path Slab Poured

  • 16 November 2018

    Main Crane Path Slab Finished, Work Starts On Upper Slabs

  • 30 November 2018

    Gulf Star Marina Time Lapse As of 11-30-18

    Here's a time lapse video we took of the old Gulf Star Marina's demolition and the creation of the footers and center slab.

  • 4 December 2018

    First Wall Panels Poured

  • 11 December 2018

    First Tilt Wall Panel Erected

  • 17 December 2018

    TIlt Wall Erection Sequence Continues

  • 17 January 2019

    Eastern Slab Poured

  • 29 January 2019

    Continue Panel Form & Pour

  • 2 May 2019

    Continue Interior Boat Bay Slab Finishing & Panel Form/Pour

  • 16 May 2019

    Continue Panel Form & Pour

  • 21 May 2019

    Continue Tilt Wall Erection Sequence

  • 24 May 2019

    Walkthrough: Continue Tilt Wall Erection Sequence

  • 20 June 2019

    Continue Tilt Wall Erection & Casting Bed Pour

  • 1 July 2019

    Final Wall Panel Erected

  • 4 July 2019

    Excavate Crane Pit & Prepare Sea Wall Renovation

  • 12 July 2019

    Old Docks Demolished

  • 20 August 2019

    Continue Seawall Construction & Pouring Boat Bay Toppings

  • 10 September 2019

    Begin Parking Lot Demolition & Building Paint

  • 11 September 2019

    Continue Pouring Boat Bay Toppings & Parking Lot Demolition

  • 18 September 2019

    Continue Construction On Parking Lot & Seawall

  • 1 November 2019

    Begin ASAR Crane Construction

  • 21 November 2019

    Install Boat Shuttle Guide Rails & Misc. Grade Work

  • 4 December 2019

    ASAR Crane Up And Running

  • 24 February 2020

    Crane Capabilities Tested With Car

  • 2 March 2020

    Architectual Elements, Piping & Crane Rails Continue

  • 24 June 2020

    Fire-Supression Foam System Tested

  • 11 August 2020

    Project Complete - Gulf Star Marina: Open For Business!